Based upon the information provided, an EHS representative may inspect the hot work location to ensure the necessary precautions outlined in the checklist below have been taken:

__________________________________________________________________________________________________________________

HOT WORK PERMIT CHECKLIST

The following precautions must been taken to prevent fire in accordance with NFPA 51B.

WITHIN 35 FEET OF WORK

  • Floors are swept clean of dust and combustibles
  • Combustible floors are wetted down or covered with damp sand, metal, or other shields
  • No combustible material, stored compressed gas cylinders, or flammable liquids are present - Combustible surfaces are protected with covers, guards, or metal shields.
  • Combustibles are moved away from opposite side of any walls
  • All wall and floor openings are covered
  • Covers are suspended beneath work to collect sparks

HOT WORK ON ENCLOSED EQUIPMENT (TANKS, CONTAINERS, DUCTS, DUST COLLECTORS, ETC.)

  • Containers are cleaned of all combustibles and purged of flammable vapors

FIRE WATCH

  • To be provided during and 60 minutes after hot work ends each day
  • Fire watcher has appropriate fire extinguisher equipment
  • Fire watcher is trained in use of fire equipment and in sounding fire alarm

FINAL CHECK

  • Final check of area must be made each day 60 minutes after completion of any hot work

PHONES

  • In the event of a fire or emergency situation call 9-1-1
  • Environmental Health & Safety, (614) 292-1284
  • Ohio State Emergency Management & Fire Prevention, (614) 292-6677

__________________________________________________________________________________________________________________

ALL NOTIFICATIONS MUST BE MADE 24-HOURS IN ADVANCE

NOTICE: All hot work smoke/fire detector enable/disable requests must come from either a project manager (PM) in Facilities Design and Construction (FDC) or a manager or higher in operations. Contractors are not allowed to contact Service 2 Facilities (S2F) directly for this request.

Requester Info

* Required
* Required
* Required
* Required

Permit Date & Time

* Required
* Required
* Required
* Required

Location

Hot Work Information

* Required
* Required
* Required
* Required

Add Supporting Documents

Add files to upload as supporting documentation along with your permit request.